Huaxian county enjoys the anniversary of the machinery factory mainly produces "celebration" brand automatic hydraulic block forming machine, semi-automatic block machine, mixer, cement foaming machine, baking-free brick machine equipment, including baking-free brick machine is one of the brick machine production equipment, baking-free brick machine has strong rigidity, dust seal, the operation is simple, durable and other characteristics, applied to baking-free brick, pipe sand brick, refractory bricks, porous brick, color pavement brick and hollow brick production, is currently the country strongly mediated environment-friendly building materials equipment.

image.png

The following is a brief introduction to how to debug the machine after installation.

The machine must be adjusted after installation of the brick machine:

1, adjust the clearance between the cylinder bottom and feeding mechanism scraper, ㎜ should be no greater than 2.

2. Adjust the gap between the bottom surface of the feeding mechanism and the large plate should not be greater than 0.

5 ㎜.

3. Adjust the adjusting ring of the upper feeding tube of feeding mechanism and the clearance between the feeding plate and the feeding disk is 0.

5-1 ㎜.

4, adjust the altitude, make out bricks, mold surface should be higher than the disk 1 ㎜ (allowing surface with a thin iron in orbit and support).

5. Adjust the eccentric shaft of the brick mechanism so that it can press out the required bricks.

6, adjust the back wheel mechanism on the pull rod, gasket and crankshaft institutions on spherical eccentric shaft to make it automatic card in the trip, the more distance in no more than 3 ㎜ cheng.

7. Adjust the adjusting nut on the vertical axis, so that the plane of the pressure template should be parallel to the plane on the rotary plate, and a 1-1 should be left.

5 ㎜ clearance.

After installation of the brick press, the test vehicle must be carried out, including the blank section and load test.

Before the test, should machine appearance inspection, tighten fastening parts, remove back wheel surface, horizontal hole and other impurities on the transmission parts, at the same time to add the lubricating oil to deal with all lubricating points, and then the artificial lift machine, wheel turning back 2-3 weeks, through inspection machine, confirm no jam phenomenon.

All inspection before empty experiment, operation time should be not less than 2 hours, the run-in test bearing temperature should be carefully observed, the gear meshing, the motor temperature rise and lubrication situation, pay attention to the brick molding mechanism and orbital roof tile parts work.

After the empty vehicle test is qualified, the feeding quantity shall be gradually increased, the load test shall be carried out, and the working conditions of each part under the load shall be checked, and the load test shall be no less than 4 hours.

Baking-free brick machine after debugging, we can avoid some problems in production process, and found the problem, the factory side can solve in time, if you are baking-free brick machine debugging work what doubts, you are welcome to call the company customer hotline.


Related Industry Knowledge

Related Products

  • Cementing Machine
  • High Quality Hammer Mill Pulverizer CE Hammer Mill Pulverizer
  • Cement High Pressure Foaming Machine
  • 4-15 Fully Automatic Block Molding Machine.
  • Building Cement Block Machine
  • Plum Shape Block Machine